Panitan-Nabas Philippines,138KV Transmit Line Project

SOURCE:adminTHE RELEASE DATA:2018-09-16 VIEWS:

菲律宾0191-1.jpg


菲律宾0191-2.jpg

Our company supported China CAMC Engineering Co.,Ltd. to implement this project. The line is 90km, double circuit. The total cost of the project is USD14,500,000. The steel tower total weight is around 3100 Tons. We purchased, supplied and delivered materials, spare parts etc.to the site. We sent four project management personnel to the site for management assistance and technical guidance. The steel tower testing is made in India JOYTI test center. The project started April of  2016 and complete in May 2017. This project got high appraisal from National Grid of the Philippines. 